-
Why I started building our own TCO sheet
-
The February purchase, and the thing that changed my mind
-
Where are Maxeon solar panels manufactured — and why it matters more than buyers think
-
We didn't go all-in on Maxeon — and we didn't reject it either
-
The TCO sheet we use for every bulk PV module decision
-
Three things I'd tell any buyer sourcing bulk PV modules
February 2024, a Tuesday afternoon in a conference room in Arizona. I had three quotes in front of me for a 1.8 MW commercial rooftop job. The spread across the three photovoltaic module manufacturers was less than two cents per watt — maybe $18,000 to $36,000 on total order value, depending on which pair I compared.
Under our old process, I'd have taken the cheapest one and moved on. Our technical team had already cleared all three.
I didn't sign. Not because I had a hunch, but because six months earlier a “best quote” on another project had turned into a $427,000 final bill — about 18% over what we'd budgeted. That one hurt enough that I stopped trusting per-watt pricing on its own.
Why I started building our own TCO sheet
For context: I run procurement at a mid-sized solar EPC. Over the past four years I've processed more than 200 module orders — distributed rooftop, small ground-mount, and a handful of OEM/private-label runs. At peak, I've been responsible for close to $4M in annual module spend.
My old logic was simple and, I thought, correct: modules are standardized products. Same certifications (IEC 61215, IEC 61730), similar wattage class, similar warranty length. So buy the cheapest one that passes engineering.
Then Q3 2023 happened.
The “cheap” vendor on a 1.2 MW project was 3.5 cents per watt under the next option — about $42,000 in savings. What actually happened: shipment arrived 11 days late and we paid standby labor; one pallet had microcracks that required a six-week replacement cycle; and the warranty claim we filed got billed back to us for return freight — about $3,200 — because that line was buried in a supplementary document instead of the main terms. Final overrun versus budget: $427,000.
That project is why I built the TCO sheet. It's not complicated — it just forces you to write down things the quote doesn't show you.
The February purchase, and the thing that changed my mind
Back to Arizona.
One of the three vendors was a Southeast Asian manufacturer that had just come online — good pricing, limited track record. One was a top-tier Chinese supplier with a standard TOPCon line. The third was Maxeon.
On first pass, Maxeon was the most expensive by a wide margin — roughly 6 to 9 cents per watt higher. On 1.8 MW, that's $108,000 to $162,000 more. On the old logic, it was out.
What kept it in the room was a comment from our lead designer. The rooftop area wasn't big enough for the array we'd originally planned at standard efficiency. With Maxeon 6 series IBC modules, we could cut the array from roughly 720 modules to about 648 — same nameplate capacity, less racking, less cable, less labor hours.
"The premium might come back on the BOS side," she said.
I'd heard that pitch before. I'd never actually run it.
So I did. Racking and labor on a commercial rooftop runs $55–$75 per module installed, depending on crew and access. Cutting 72 modules saves roughly $4,000 to $5,400 on balance-of-system alone. That closed the gap to about $60,000 — still real money, but no longer a 30% premium.
Then I ran the temperature coefficient. Maxeon's IBC cells sit around -0.29%/°C for Pmax. Standard PERC runs closer to -0.35%/°C. That sounds like a rounding error until you model it at 65°C cell temperature in an Arizona summer — where the gap in actual kWh over a year lands somewhere in the 3–5% range. Over 25 years of production, that's material.
Here's the honest admission: I'd been treating a system-level decision like a single-item purchase. That was my mistake, not the vendors'.
Where are Maxeon solar panels manufactured — and why it matters more than buyers think
When we got to due diligence, I had our team verify manufacturing origin, because two things ride on it: tariff exposure and customer-facing supply chain traceability.
Maxeon's manufacturing footprint spans Malaysia, Mexico, and the Philippines, with US capacity planned/expanding in Albuquerque, New Mexico. The company spun out of SunPower in 2020, and the origin picture isn't a single answer — it depends on cell fabrication vs. module assembly vs. final shipment point.
What we now require in every PO: three separate origin fields — cell origin, module assembly location, and port of export. Any change requires written notice. Not a nice-to-have. A change in any of those three can shift your landed cost and your customs classification.
Most procurement teams skip this step. Then they find out at clearance.
We didn't go all-in on Maxeon — and we didn't reject it either
Final call on that 1.8 MW job: split award.
The area-constrained rooftop portion went to Maxeon 6. The remaining ground array went to the cheaper TOPCon supplier, where land wasn't a constraint and the efficiency premium had nowhere to earn back.
That split is the actual lesson. Not “Maxeon is best” and not “Maxeon is overpriced.” It's that no bulk PV module choice is universal.
Here's my honest read on where Maxeon doesn't fit:
- Utility-scale ground-mount with abundant land. When racking and labor are spread thin across megawatts, efficiency premium doesn't pay back. Price per watt dominates. Maxeon isn't the right call here.
- Customers with extremely tight CAPEX and constrained financing. The higher upfront cost pushes simple payback out further than some of these buyers can accept. If that's your buyer, look elsewhere.
And where it does:
- Area-constrained rooftops — where you literally can't fit more modules.
- High-temperature, high-irradiance sites — where the temperature coefficient compounds over decades.
- Projects where 40-year warranty backing matters — for financing, insurance, or asset resale.
Outside those three, run the numbers before you sign a premium. And I say that as someone who has now signed one.
The TCO sheet we use for every bulk PV module decision
The questions everyone asks are “what's your price per watt?” and “what's the efficiency?” The questions they should be asking are “what's the warranty claim process?” and “what does this do to my system-level cost?”
Our sheet takes about 40 minutes per project. Fields:
- Price per watt — sourced and timestamped. Quotes move weekly; an unlabeled number is worthless.
- Origin — three fields (cell, assembly, port). See above.
- Temperature coefficient — modeled against on-site irradiance and cell temperature, not nameplate STC.
- Warranty claim logistics — who pays return freight? This varies wildly and is almost always in an annex.
- System-side delta — module count change, racking, cable, labor.
- Delivery reliability — trailing 12-month on-time rate, not average lead time.
- End-of-life terms — resale, recycling, and disposal responsibility.
The sheet isn't fun to fill out. But it's the reason we now catch the $400K overrun before it happens instead of after.
Three things I'd tell any buyer sourcing bulk PV modules
One: Don't pay for efficiency. Pay for efficiency that this specific project can actually monetize.
Two: Origin goes in the contract, not the email thread.
Three: No manufacturer — Maxeon included — should be a default. The default is your TCO sheet.
I still get the same question from peers: "Is Maxeon worth it?" The honest answer is that it depends on about six variables, and four of them are on your project, not on their datasheet. Anyone who gives you a yes-or-no without asking those questions is selling, not advising.
Note to self: run the BOS delta even when the module count doesn't change. We got lucky on that assumption twice this year.